Lead times on everyday chips are stretching again. On its November 5, 2026 earnings call, Microchip Technology said most of its standard products, which historically shipped in 4 to 8 weeks, now carry lead times of 6 to 32 weeks. Several manufacturer ordering deadlines for older parts also fall between now and next summer. This post explains what changed and lists five dates worth checking against your parts list.

What did Microchip say?

Microchip makes microcontrollers, the small processors that run machines and instruments, along with analog and interface chips. Its parts are common in industrial, medical, aerospace and defense equipment.

CEO Steve Sanghi told analysts that AI customers have filled capacity at the outside companies that package and test chips. In his words, AI companies “took over the whole factory.” He also said data center demand is crowding out capacity on older manufacturing processes, and that in some cases the company cannot get substrates, the base material a chip is mounted on.

Two details matter for buyers:

  • It is a range, not an average. Some products still quote 6 weeks. Some quote 32. Microchip did not say which product lines sit at the long end, so check your own part numbers before assuming either way.
  • A price round is expected in January. Sanghi said most major foundries (the factories that make chips for other companies) and packaging houses plan another round of increases starting then. Microchip said it plans to absorb the increase for now and has not decided what happens after that.

Is this one company or a wider pattern?

Other data points the same direction. In the Institute for Supply Management’s October survey of U.S. factory purchasing managers, electronic components were listed as in short supply for the 20th consecutive month, memory for the 10th and printed circuit boards for the 4th. Average lead time for production materials of all kinds rose to 87 days. One respondent in the machinery industry wrote that a lead time of “four weeks is now 50 weeks.” That is a single buyer’s report, not a market average.

Not every signal agrees. The Electronic Components Industry Association’s October survey showed the industry’s sales outlook for November falling 19.2 points to 112.4, the steepest one-month drop since June 2022. A reading above 100 still means growth is expected, and a sales outlook is not the same thing as a lead time. It is a fair reminder that conditions vary a great deal from part to part.

That is the practical point. Headlines describe the market. Dates and part numbers describe your build.

Red marker circling a date on a paper calendar, representing a last-time-buy ordering deadline

Five dates to check against your parts list

DateWhat happensWhat to check
November 30, 2026Renesas stops taking orders on 92 older memory part numbers (notice EOL260016). The reason given is aging equipment in the wafer process. 14 of the parts have no listed replacement. Last shipments are by December 31, 2028, and orders cannot be cancelled or returned.Part numbers starting R1LP, R1LV, R1RP, R1RW, RMLV or RMWV.
January 2027Most major foundries and packaging houses are expected to raise prices again, according to Microchip’s CEO.How long your current quotes hold, especially on microcontrollers, analog and power chips.
July 29, 2027Analog Devices closes orders on parts made at two older TSMC factories in Taiwan that are shutting down. Last shipments are January 29, 2028.Data converters, op amps and comparators, regulators and supervisors, temperature sensors, RS-485 transceivers, older microcontrollers and DSPs. Ask your Analog Devices contact for the affected list.
August 6, 2027NXP closes orders on older parts made at its Chandler, Arizona site, which is being sold (notice 202608007DN). Last deliveries are August 6, 2028. NXP lists these parts as limited availability, so the date is not a guarantee of supply. Confirm your own deadline with NXP.MC33 and MC34 analog and power parts, MC56F8 motor-control chips, older 8-bit microcontrollers such as MC9S08 and MC908.
End of 2030Samsung will reportedly stop making chips on its older 8-inch lines, and TSMC is reportedly moving about 80% of its own 8-inch capacity to an affiliate, according to industry press cited by TrendForce. Neither company has confirmed this publicly.Long-life products that depend on power, analog and microcontroller chips built on older processes. These may be affected.
Ordering deadlines and price dates for buyers, as of November 2026. Confirm dates with each manufacturer.

A 2027 deadline is closer than it looks. A last-time buy needs a forecast that covers repairs and service for the life of the product, a budget, and sometimes a redesign and re-qualification if a replacement part is involved. That work takes months.

What should buyers check this week?

  1. Reconfirm delivery dates on open orders for microcontrollers, analog and power chips. Ask for the current lead time in writing.
  2. Compare your bill of materials to the three notices above. Matching on the part-number prefixes takes a few minutes and tells you whether a deadline applies to you.
  3. Ask how long current pricing holds past January.
  4. Size any last-time buy from firm forecasts, including service and repair demand. These orders usually cannot be cancelled, so buy to a number you can defend.
  5. Know where every part came from. This is the step that gets skipped when a build date is at risk, and it matters most.

Where the counterfeit risk comes in

Long lead times and closed order books do not create counterfeit parts. They change where buyers have to look. When the manufacturer can no longer supply a part, the remaining stock sits on shelves around the world, and demand from repairs outlasts it by years. Discontinued memory, analog and microcontroller parts from well-known brands are long-standing targets for remarking, where a used or lower-grade part is relabeled to look like the one you need.

That is why verification exists. At AERI, every part goes through our in-house QC lab before it ships, with inspection and testing to recognized industry standards. Our Counterfeit Detection Guide walks through what inspectors look for, from marking and surface texture to internal characteristics.

AERI was founded by Robb Hammond, a founding member and former committee chair of the SAE AS6081 Standard created for the avoidance of counterfeit electronic components. We have sourced obsolete, allocated and hard-to-find components since 1994.

Have a part on one of these lists, or an order that just slipped? Send us the part number.


FAQ

Are semiconductor lead times getting longer?
For some parts, yes. Microchip said in November 2026 that lead times on most of its standard products went from a historical 4 to 8 weeks to a range of 6 to 32 weeks. U.S. factory buyers have listed electronic components as in short supply for 20 straight months in the ISM survey.

Why are lead times longer if the chips are not for AI?
Everyday chips share packaging lines, test lines and older factory capacity with parts built for AI data centers. Microchip’s CEO said AI customers have filled much of that capacity.

What is a last-time buy?
It is the final date a manufacturer will accept orders for a part it is discontinuing. After that date, the part is available only from stock that already exists.

What happens to parts when a chip factory closes?
Parts that cannot move to another factory are discontinued together. Buyers get one ordering window, then rely on existing stock for the rest of the product’s life.

How do I avoid counterfeit parts when buying discontinued components?
Buy from suppliers that inspect and test parts before shipping, ask for documentation of where the parts came from, and take extra care with commonly remarked categories such as memory and microcontrollers. See AERI’s Counterfeit Detection Guide.